'''This page is a personal project of Eric Stein. He's working on getting quotes from electrican(s) to get this work done.'''
+
'''Eric Stein's working on getting quotes from electrican(s) to get this work done.'''
  
==Woodshop==
+
== Woodshop ==
  
Drops at sawstop, and multiple at each table row. TODO: Determine if this is accurate.
+
Reel drops at sawstop, and multiple at each table row.
 +
Sawstop + dust manager need more power.
  
==Electronics==
+
== Electronics ==
  
1. We need 2 drops of three phase 50 Amp in the metal shop. Any where along the long wall.
+
1. The ceiling extension cord in the electronics lab needs to be replaced with surface wiring. Three boxes spaced where the retractable drops are located. Do reel drops. '''Not going to do this, Tom says it's fine'''.
  
2. The ceiling extension cord in the electronics lab needs to be replaced with surface wiring. Three boxes spaced where the retractable drops are located.
+
2. Since we are doing electrical we also need addition outlets on the opposite side of the ceiling in front of the the projection wall and white boards. I would suggest additional 3 outlet boxes spaced the same as the surface wiring to replace the yellow extension cord. Same drops as the other part of the room.
  
3. Since we are doing electrical we also need addition outlets on the opposite side of the ceiling in front of the the projection wall and white boards.  I would suggest additional 3 outlet boxes spaced the same as the surface wiring to replace the yellow extension cord.
+
== Kitchen ==
 
 
==Kitchen==
 
  
 
GHCI outlet by sink.
 
GHCI outlet by sink.
TBD remainder on walls.
 
 
Fix bent electrical drop from ceiling.
 
Fix bent electrical drop from ceiling.
3 phase for the beer brewing fermenter system.
 
  
==Lounge==
+
== Lounge ==
  
 
Fix exposed wiring, which there is now more of.
 
Fix exposed wiring, which there is now more of.
 +
Outlets as needed to solve the extension cords issue.
  
==Metal Shop==
+
== Metal Shop ==
  
 
The circuit that goes along the shop side of the shop (wood, metal) with the really long conduit, is one circuit. It trips sometimes if people are using everything.
 
The circuit that goes along the shop side of the shop (wood, metal) with the really long conduit, is one circuit. It trips sometimes if people are using everything.
  
==General Shop Area==
+
Run a new circuit from the panel inside the shop, run power off of there. Shorten the wood shop circuit so it doesn't extend to metal.
  
Fix drops that are not on stiff supports or use the wrong kind of conduit.
+
== General Shop Area ==
 +
 
 +
Fix drops that are not on stiff supports or use the wrong kind of conduit. Where there are no drops, we should add some.
 +
Everything should be metered to avoid having 220 where it's not supposed to be 220 and vice versa.
 
Fix breaker boxes to be properly screwed shut.
 
Fix breaker boxes to be properly screwed shut.
 
Map breakers.
 
Map breakers.
Power for eventual hot metal and glass room?
+
 
 +
[[Category:Facilities]]

Latest revision as of 14:13, 17 March 2014

Eric Stein's working on getting quotes from electrican(s) to get this work done.

Woodshop

Reel drops at sawstop, and multiple at each table row. Sawstop + dust manager need more power.

Electronics

1. The ceiling extension cord in the electronics lab needs to be replaced with surface wiring. Three boxes spaced where the retractable drops are located. Do reel drops. Not going to do this, Tom says it's fine.

2. Since we are doing electrical we also need addition outlets on the opposite side of the ceiling in front of the the projection wall and white boards. I would suggest additional 3 outlet boxes spaced the same as the surface wiring to replace the yellow extension cord. Same drops as the other part of the room.

Kitchen

GHCI outlet by sink. Fix bent electrical drop from ceiling.

Lounge

Fix exposed wiring, which there is now more of. Outlets as needed to solve the extension cords issue.

Metal Shop

The circuit that goes along the shop side of the shop (wood, metal) with the really long conduit, is one circuit. It trips sometimes if people are using everything.

Run a new circuit from the panel inside the shop, run power off of there. Shorten the wood shop circuit so it doesn't extend to metal.

General Shop Area

Fix drops that are not on stiff supports or use the wrong kind of conduit. Where there are no drops, we should add some. Everything should be metered to avoid having 220 where it's not supposed to be 220 and vice versa. Fix breaker boxes to be properly screwed shut. Map breakers.