3519 Electrical Work

From Pumping Station One
Revision as of 00:51, 1 May 2013 by Toba (talk | contribs)
Jump to navigation Jump to search

This page is a personal project of Eric Stein. He's working on getting quotes from electrican(s) to get this work done.

Woodshop

Drops at sawstop, and multiple at each table row. TODO: Determine if this is accurate.

Electronics

1. We need 2 drops of three phase 50 Amp in the metal shop. Any where along the long wall.

2. The ceiling extension cord in the electronics lab needs to be replaced with surface wiring. Three boxes spaced where the retractable drops are located.

3. Since we are doing electrical we also need addition outlets on the opposite side of the ceiling in front of the the projection wall and white boards. I would suggest additional 3 outlet boxes spaced the same as the surface wiring to replace the yellow extension cord.

Kitchen

GHCI outlet by sink. TBD remainder on walls. Fix bent electrical drop from ceiling. 3 phase for the beer brewing fermenter system.

Lounge

Fix exposed wiring.

Metal Shop

Talk to Mike.

General Shop Area

Fix drops that are not on stiff supports or use the wrong kind of conduit. Fix breaker boxes to be properly screwed shut. Map breakers. Power for eventual hot metal and glass room?