== Status ==
 
== Status ==
  
Fuse repaired. Seems to be working. COM 6.
+
Components are all there, but the unit needs some work before becoming fully operational. See "Maintenance" notes below.
  
 
== Authorization ==
 
== Authorization ==
Line 27: Line 27:
  
 
== Maintenance ==
 
== Maintenance ==
 +
 +
9.7.2016 - Danny Blanchard: Machine cleaned, belts tensioned, power supplies temporarily mounted to wall, wires organized and secured with zip ties.  Spindle control and E-Stops tested, both working.
 +
 +
Items that still need work:
 +
1. Waste board repaired or replaced. Entire board is unsupported in the middle, causing it to sag.  Also, one stud has pulled up a volcano-like mountain in one part of the waste board, and needs to be milled down.  Recommend getting two $7 20mmx20mmx300mm extrusions (from Inventables or elsewhere) and T-nuts to support it in the middle (this is a common upgrade for this particular machine).
 +
 +
2. Y-axis cable/energy chain is too short, binding before the gantry can reach Y-zero.  I have two brackets I'm going to install that will relocated the chain about 1 inch, and this will do the trick (found this solution online from another SO2 user).
 +
 +
3. Bearing blocks on all axis need to be tuned.  Some are not making contact, and gantry is not square to waste board.
 +
 +
4. E-stop case is glued shut, but the nut on the back of the switch has backed off.  I'm going to drill a small hole parallel to the nut to allow manual tightening without having to break open this nice case.  Case should be permanently mounted in an easy-access location on the frame.
 +
 +
5. Spindle PWM, both power supplies, and perhaps the GRBLShield should be mounted in a compact, fan-cooled enclosure.  I'd love said enclosure to be part of a full machine enclosure that incorporates noise suppression, interior lighting, and dust collection.
 +
 +
6. Install Homing and limit switches, and connect to GRBLShield.  This should prevent some crashes.
 +
 +
7. General wiring clean-up and sheathing: some connectors have bare leads exposed, and I'd love to clean up the build by sheathing many of the wires.
 +
 +
8. Label axis, electrical components, etc with a label-maker for ease of understanding.
  
 
== Documentation ==
 
== Documentation ==

Revision as of 20:24, 7 September 2016


ShapeOko2 CNC Router
Owner/Loaner PS:One
Serial Number 5549
Make/Model ShapeOko 2 "The Works" version
Arrival Date 2014
Usability no
Contact CNC Area Host
Where CNC table in the shop
Authorization Needed yes
Hackable no
Estimated Value $1000
Host Area CNC


ShapeOko2 CNC Router Area: CNC https://wiki.pumpingstationone.org/wiki/ShapeOko2_CNC_Router



Status

Components are all there, but the unit needs some work before becoming fully operational. See "Maintenance" notes below.

Authorization

Preflight Checklist

Known Issues

Modifications

Maintenance

9.7.2016 - Danny Blanchard: Machine cleaned, belts tensioned, power supplies temporarily mounted to wall, wires organized and secured with zip ties. Spindle control and E-Stops tested, both working.

Items that still need work: 1. Waste board repaired or replaced. Entire board is unsupported in the middle, causing it to sag. Also, one stud has pulled up a volcano-like mountain in one part of the waste board, and needs to be milled down. Recommend getting two $7 20mmx20mmx300mm extrusions (from Inventables or elsewhere) and T-nuts to support it in the middle (this is a common upgrade for this particular machine).

2. Y-axis cable/energy chain is too short, binding before the gantry can reach Y-zero. I have two brackets I'm going to install that will relocated the chain about 1 inch, and this will do the trick (found this solution online from another SO2 user).

3. Bearing blocks on all axis need to be tuned. Some are not making contact, and gantry is not square to waste board.

4. E-stop case is glued shut, but the nut on the back of the switch has backed off. I'm going to drill a small hole parallel to the nut to allow manual tightening without having to break open this nice case. Case should be permanently mounted in an easy-access location on the frame.

5. Spindle PWM, both power supplies, and perhaps the GRBLShield should be mounted in a compact, fan-cooled enclosure. I'd love said enclosure to be part of a full machine enclosure that incorporates noise suppression, interior lighting, and dust collection.

6. Install Homing and limit switches, and connect to GRBLShield. This should prevent some crashes.

7. General wiring clean-up and sheathing: some connectors have bare leads exposed, and I'd love to clean up the build by sheathing many of the wires.

8. Label axis, electrical components, etc with a label-maker for ease of understanding.

Documentation

ShapeOko 2 wiki for assembly, use, and source files.

Certified Users

qualified member trained by
Elizabeth Herself as she built it
Clarence Risher Elizabeth
Ron Olson Elizabeth
Darold Higa Elizabeth
Aaron Mintz Elizabeth
Michael Solheim Elizabeth
Eric Beauchamp Elizabeth
Roger Moore Elizabeth
Kyle Bieneman Elizabeth
Andrew Camardella Elizabeth
Todd Allen Elizabeth
Sam Reicks Andrew Camardella
Ray Doeksen Sevin Strauss
Leon Grossman Sevin Strauss
Ryan Taylor Leon Grossman
Simon Pyle Sevin Strauss
Ralph Brendler Arturo Duarte
Jeremy fay Arturo Duarte