Line 33: Line 33:
 
** Compressed air for the laser and hot metals. $300
 
** Compressed air for the laser and hot metals. $300
  
*Obtain necessary permits if they are deemed appropriate.
+
*Demolition
*Remove temporary partition in new lounge. Paint and repair drywall if necessary.  Materials: paint.
+
** Remove temporary partition in new lounge. Paint and repair drywall if necessary.  Materials: paint.
*Move equipment to new locations.
+
** Remove tool cage walls.
 +
 
 +
* Obtain necessary permits if they are deemed appropriate.
 +
* Move equipment to new locations.
 
* Vacuum dust from trusses, walls, etc. in 3519 shop.  
 
* Vacuum dust from trusses, walls, etc. in 3519 shop.  
*Remove tool cage walls.
+
* Purchase and install shelving for member storage. $500
*Purchase and install shelving for member storage. $500
+
* Benches for general work area.
*Benches for general work area.
 
 
* Rent or purchase a section of rolling scaffolding.  This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $300
 
* Rent or purchase a section of rolling scaffolding.  This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $300
  

Revision as of 21:23, 28 June 2016

Sponsors

  • Dean Anderson
  • Everett Wilson

History

  • Mailing List Announcement:
  • Officially Proposed:
  • To be Voted on:

Background

We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).

This Build-Out vote describes the initial build-out of the combined space. The type of wall or partition required to separate woodworking and hot metals has not been determined, so an estimate for that is not included. A vote for additional money for the wall may be necessary.

The 2016 budget vote allocated $5000 for build-out. The expenses for the activities listed below should fall within that budget. If there are unforeseen expenses another vote may be necessary.

  • HVAC
    • Install AC in new lounge. $300
    • Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser. The roof perforation will be done by a professional roofer. Interior ducting can be done by volunteers. Makeup air? Materials: ducting, elbows, hangers. $300
    • Install ventilation duct and fan for the kitchen. Use the duct currently used by the laser. $300
    • Install ventilation duct and fan for small metals (jewelry). $300
    • Move dust collection system for woodworking. Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system. $900
    • Extend ventilation duct and add hood for hot metals. ??
  • Electrical
    • Install new power outlets for woodworking, cold metals and hot metals. Materials: conduit, wire, outlets. $1500
  • Plumbing
    • Install work sink on the wall adjacent to the kitchen, next to the sliding fire door. Materials: sink, misc. plumbing. $300
    • Install work sink at the top of the stairs next to upstairs bathroom. $300
    • Remove old sink in new lounge.
    • Compressed air for the laser and hot metals. $300
  • Demolition
    • Remove temporary partition in new lounge. Paint and repair drywall if necessary. Materials: paint.
    • Remove tool cage walls.
  • Obtain necessary permits if they are deemed appropriate.
  • Move equipment to new locations.
  • Vacuum dust from trusses, walls, etc. in 3519 shop.
  • Purchase and install shelving for member storage. $500
  • Benches for general work area.
  • Rent or purchase a section of rolling scaffolding. This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $300

This vote assumes that these tasks will be performed by the landlord before we move in:

  • Paint the walls.
  • Fix roof leaks.
  • Upgrade the lighting.

Language

We authorize the board to spend up to $xxxx for tools, materials, supplies and services to buildout plan X.

We also authorize the board to select a project manager who will create a plan, track expenses, organize volunteers and hire contractors. The project manager will provide periodic reports to the board. The project manager will consult with the membership, area hosts, board and space planning committee when appropriate.

The funding for this vote will expire at the end of 2016.

Receipts

Voting

xx Yea, xx Nay, xx Present

Quorum was xx