Difference between revisions of "Vote to Fund Space Expansion Buildout"

From Pumping Station One
Jump to navigation Jump to search
Line 18: Line 18:
 
* HVAC
 
* HVAC
 
** Install AC in new lounge. $300
 
** Install AC in new lounge. $300
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers. $300
+
** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser.  The roof perforation will be done by a professional roofer.  Interior ducting can be done by volunteers.  Makeup air? Materials: ducting, elbows, hangers. $400
** Install ventilation duct, fan and hood for the kitchen.  Use the duct currently used by the laser. $300
+
** Install ventilation duct, fan and hood for the kitchen.  Use the duct currently used by the laser. $250
** Install ventilation duct and fan for small metals (jewelry).  $300
+
** Install ventilation duct and fan for small metals (jewelry).  $250
 
** Move dust collection system for woodworking.  Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system. $900
 
** Move dust collection system for woodworking.  Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system. $900
 
** Extend ventilation duct and add hood for hot metals. $400
 
** Extend ventilation duct and add hood for hot metals. $400
Line 31: Line 31:
 
** Install work sink at the top of the stairs next to upstairs bathroom. $300
 
** Install work sink at the top of the stairs next to upstairs bathroom. $300
 
** Remove old sink in new lounge.
 
** Remove old sink in new lounge.
** Compressed air for the laser and hot metals. $300
+
** Compressed air lines for the laser and hot metals. $250
  
 
* Partition between hot metals and woodworking in 3515.
 
* Partition between hot metals and woodworking in 3515.
Line 52: Line 52:
 
*Fix roof leaks.
 
*Fix roof leaks.
 
*Upgrade the lighting.
 
*Upgrade the lighting.
 +
 +
Sub total: $7750
 +
        + 20% contingency funds
 +
        - $5000 already allocated
 +
Total      $4300
  
 
== Language ==
 
== Language ==

Revision as of 01:31, 29 June 2016

Sponsors

  • Dean Anderson
  • Everett Wilson

History

  • Mailing List Announcement: 6/28/16
  • Officially Proposed:
  • To be Voted on:

Background

We signed the lease for the 3515 Elston and will move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link).

This vote describes the tasks required for the initial build-out of the combined space.

The 2016 budget vote allocated $5000 for build-out. This vote covers the expected expenses beyond that allocation.

  • HVAC
    • Install AC in new lounge. $300
    • Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser. The roof perforation will be done by a professional roofer. Interior ducting can be done by volunteers. Makeup air? Materials: ducting, elbows, hangers. $400
    • Install ventilation duct, fan and hood for the kitchen. Use the duct currently used by the laser. $250
    • Install ventilation duct and fan for small metals (jewelry). $250
    • Move dust collection system for woodworking. Materials: ducting, elbows, wyes, hangers blast gates. Purchase new filter for the Jet collector to aid with the transition to the new system. $900
    • Extend ventilation duct and add hood for hot metals. $400
  • Electrical
    • Install new power outlets for woodworking, cold metals and hot metals. Materials: conduit, wire, outlets. $1500
  • Plumbing
    • Install work sink on the wall adjacent to the kitchen, next to the sliding fire door. Materials: sink, misc. plumbing. $300
    • Install work sink at the top of the stairs next to upstairs bathroom. $300
    • Remove old sink in new lounge.
    • Compressed air lines for the laser and hot metals. $250
  • Partition between hot metals and woodworking in 3515.
    • We are still investigating the options allowed by city and fire codes. Best guess of cost is $1500. If code requirements force this higher, we will have discussion and another vote before proceeding.
  • Demolition
    • Remove temporary partition in new lounge. Paint and repair drywall if necessary. Materials: paint.
    • Remove tool cage walls.
  • Obtain necessary permits if they are deemed appropriate.
  • Move equipment to new locations.
  • Vacuum dust from trusses, walls, etc. in 3519 shop.
  • Purchase and install shelving for member storage. $500
  • Benches for general work area. $500
  • Rent or purchase a section of rolling scaffolding. This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $400

This vote assumes that these tasks will be performed by the landlord before we move in:

  • Paint the walls.
  • Fix roof leaks.
  • Upgrade the lighting.

Sub total: $7750

        + 20% contingency funds
        - $5000 already allocated

Total $4300

Language

We authorize the board to spend up to $xxxx for tools, materials, supplies and services to build-out plan 1 as described by the Space Planning Committee.

We also authorize the board to select a project manager who will create a plan, track expenses, organize volunteers and hire contractors. The project manager will provide periodic reports to the board. The project manager will consult with the membership, area hosts, board and space planning committee when appropriate.

The funding for this vote will expire at the end of 2016.

Receipts

Voting

xx Yea, xx Nay, xx Present

Quorum was xx