=Background=
 
=Background=
  
The main purpose of this vote is twofold: take advantage of space that became available during the space expansion and reinstate the expired kitchen renovation budget with some modifications. One space issue that has become evident is the disconnect between the kitchen and the lounge, so this vote seeks to provide options for the membership to decide if the Kitchen Area should move over to occupy what was once slotted to be the small metals area. This area is now officially general area space, and is now being occupied by cold metals, and both areas are in agreement with the possible move.
+
The main purpose of this vote is twofold: take advantage of space that became available during the space expansion and allow the use of funds for a renovation budget. A former renovation budget was unused due to the space expansion effors; this new renovation budget mirrors the previous budget with some modifications. One space issue that has become evident is the disconnect between the kitchen and the lounge. This vote seeks to make a more fluid space for the membership by directly connecting the kitchen and lounge, without having to pass through another area. This move is accomplished by taking up some space originally intended for small metals, is considered part of the general area, and is now being occupied by cold metals. Both General area and Cold Metals  are in agreement with the possible move.
  
Plans are provided showing the two different floor layouts that may occur should one of the proposed plans in this vote pass. This vote is to decide if we should pursue a new plan A over the old plan B when the renovation takes place. This vote also includes a budget valid for either of the proposed plans.
+
Plans are provided showing the two different floor layouts. This vote calls for Plan A to be implemented with the provision of an appropriate budget. Plan B, in comparison, is the current kitchen area renovated with the same equipment and infrastructure as the space the new proposed space.
  
 
[[File:Kitchen-plan-A-2017.jpg]]
 
[[File:Kitchen-plan-A-2017.jpg]]
Line 27: Line 27:
  
 
====Beer Church====
 
====Beer Church====
The long-standing beer church has housed all of it's equipment and fermentation chamber in the kitchen area. The kitchen area no longer has a desire to host beer church within its confines and would like to transfer it to the General area (for which there is support in General Area). At some point during the expansion some part of Beer church was partially displaced to the dock area which has been determined to be an unsuitable location. All of beer church will be housed in a specific location withing the General area depending on which plan is chosen. In plan A beer church will be consolidated to the fermentation chamber's current wall with a total depth of 3 ft from the wall from the kitchen doorway to the north wall. In plan B beer church will move on the short outside wall of the kitchen from the outside corner of the kitchen to the outside of the kitchen pass-through ust out
+
The long-standing beer church has housed all of it's equipment and fermentation chamber in the kitchen area. The kitchen area no longer has a desire to host beer church within its confines and would like to transfer it to the General area (for which there is support in General Area). All of beer church will be housed in a specific location within the General area depending on which plan is chosen. In plan A beer church will be consolidated to the fermentation chamber's current wall with a total depth of 3 ft from the wall from the kitchen doorway to the north wall. In plan B beer church will move on the short outside wall of the kitchen from the outside corner of the kitchen to the outside of the kitchen pass-through ust out
  
 
== Budgeting ==   
 
== Budgeting ==   
 
 
As the membership grows, so does the need for storage, improved hygienic conditions and further dining accommodations in the kitchen.  Our goal is to bring the current kitchen inline with a commercial kitchen, providing a space for safe food preparation.
 
As the membership grows, so does the need for storage, improved hygienic conditions and further dining accommodations in the kitchen.  Our goal is to bring the current kitchen inline with a commercial kitchen, providing a space for safe food preparation.
  
Line 36: Line 35:
  
 
* Donated Commercial Range - Free
 
* Donated Commercial Range - Free
* Range vent hood ~ $1500.00
+
* Range vent hood ~ $1000.00
* Range and vent hood installation cost ~ $3000
+
* Range and vent hood installation cost ~ $2000
 
*<s> Install a 10" ventilation duct for the commercial range in the kitchen ~$300.00 </s> COMPLETED
 
*<s> Install a 10" ventilation duct for the commercial range in the kitchen ~$300.00 </s> COMPLETED
* Cubby/Electrical Build-out ~$100.00 - A cubby hole extending into the general area needs to be built to make room for the commercial range.
+
* Cubby/Electrical Build-out ~$150.00 - A cubby hole extending into the general area needs to be built to make room for the commercial range.
* Cabinetry and wall re-framing/re-enforcing ~$1500.00 - Depending The kitchen will be expanding with the relocation of beer church.  Upper and lower cabinets will be installed in this new dining area.
+
* Cabinetry and wall re-framing/re-enforcing ~$1200.00 - Depending The kitchen will be expanding with the relocation of beer church.  Upper and lower cabinets will be installed in this new dining area.
 
* Flooring Resurfacing - Leftover supplies from Lounge 2.0 and CNC areas will be used to resurface the kitchen floor with epoxy paint.
 
* Flooring Resurfacing - Leftover supplies from Lounge 2.0 and CNC areas will be used to resurface the kitchen floor with epoxy paint.
* Additional Equipment ~$600.00 - Pantry/dry food storage, stainless steel island cart w/casters, stainless steel table/s.
+
* Additional Equipment ~$800.00 - Pantry/dry food storage, stainless steel island cart w/casters, stainless steel table/s; purchases can be made affordably at restaurant auctions.
  
 
===Optional Renovation Enhancements===
 
===Optional Renovation Enhancements===
Line 49: Line 48:
  
 
*Sanitary, heat resistant dining table and chairs/stools
 
*Sanitary, heat resistant dining table and chairs/stools
 +
*Faucet sprayer attachments
 
*Backsplash tiles
 
*Backsplash tiles
 
*Stainless Steel corner tables
 
*Stainless Steel corner tables
Line 55: Line 55:
 
*Metal rack
 
*Metal rack
 
   
 
   
   Sub total:  $3700
+
   Sub total:  $5150
   -plus 20% contingency funds         
+
   -plus ~15% contingency funds         
   Total:  $4440.00
+
   Total:  $6000
  
  
 
===Language===
 
===Language===
  
We authorize the board to shift the kitchen area as per the recommendation of the membership based on the 2 proposed plans. We authorize the board to spend up to $4200.00 for equipment, materials, and supplies to renovate the kitchen. The budgeted funds are valid for 6 months after the passing of this vote.
+
We authorize the board to allocate space for the kitchen area as defined in Plan A. We authorize the board to spend up to $6000.00 for equipment, materials, and supplies to renovate the kitchen. The budgeted funds are valid for 8 months after the passing of this vote.
 
 
====Vote Options:====
 
Yes to Plan A with Budget
 
 
 
Yes to Plan B with Budget
 
 
 
No
 

Revision as of 05:11, 22 September 2017

Background

The main purpose of this vote is twofold: take advantage of space that became available during the space expansion and allow the use of funds for a renovation budget. A former renovation budget was unused due to the space expansion effors; this new renovation budget mirrors the previous budget with some modifications. One space issue that has become evident is the disconnect between the kitchen and the lounge. This vote seeks to make a more fluid space for the membership by directly connecting the kitchen and lounge, without having to pass through another area. This move is accomplished by taking up some space originally intended for small metals, is considered part of the general area, and is now being occupied by cold metals. Both General area and Cold Metals are in agreement with the possible move.

Plans are provided showing the two different floor layouts. This vote calls for Plan A to be implemented with the provision of an appropriate budget. Plan B, in comparison, is the current kitchen area renovated with the same equipment and infrastructure as the space the new proposed space.

Kitchen-plan-A-2017.jpg

Kitchen-plan-B-2017.jpg

Two-plans-overlapped.jpg

Benefits of Plan A over Plan B

  • More convenient access from kitchen area to all other departments.
  • Ability to host more people in the lounge for events if the food is fully accessible in the kitchen.
  • Beer church and all of it’s equipment can remain where it is currently stationed.
  • The linens and dishes cabinet will be located more conveniently by the sink.
  • Noise buffering between the lounge and general shop area.
  • General area in the shop becomes contiguous.

Complications

An extra wall, ceiling, and doorway (1.5 doorway like those leading out of the foyer) will have to be installed and the view from one end of the building to the other will change.

Cold Metals

Cold metals will have to shift equipment (for which there is support in the cold metals area).

Beer Church

The long-standing beer church has housed all of it's equipment and fermentation chamber in the kitchen area. The kitchen area no longer has a desire to host beer church within its confines and would like to transfer it to the General area (for which there is support in General Area). All of beer church will be housed in a specific location within the General area depending on which plan is chosen. In plan A beer church will be consolidated to the fermentation chamber's current wall with a total depth of 3 ft from the wall from the kitchen doorway to the north wall. In plan B beer church will move on the short outside wall of the kitchen from the outside corner of the kitchen to the outside of the kitchen pass-through ust out

Budgeting

As the membership grows, so does the need for storage, improved hygienic conditions and further dining accommodations in the kitchen. Our goal is to bring the current kitchen inline with a commercial kitchen, providing a space for safe food preparation.

The following will be included in this vote:

  • Donated Commercial Range - Free
  • Range vent hood ~ $1000.00
  • Range and vent hood installation cost ~ $2000
  • Install a 10" ventilation duct for the commercial range in the kitchen ~$300.00 COMPLETED
  • Cubby/Electrical Build-out ~$150.00 - A cubby hole extending into the general area needs to be built to make room for the commercial range.
  • Cabinetry and wall re-framing/re-enforcing ~$1200.00 - Depending The kitchen will be expanding with the relocation of beer church. Upper and lower cabinets will be installed in this new dining area.
  • Flooring Resurfacing - Leftover supplies from Lounge 2.0 and CNC areas will be used to resurface the kitchen floor with epoxy paint.
  • Additional Equipment ~$800.00 - Pantry/dry food storage, stainless steel island cart w/casters, stainless steel table/s; purchases can be made affordably at restaurant auctions.

Optional Renovation Enhancements

Should the budget allow due to savings from the purchase of discounted and/or donated materials, the below shall be included in this vote.

  • Sanitary, heat resistant dining table and chairs/stools
  • Faucet sprayer attachments
  • Backsplash tiles
  • Stainless Steel corner tables
  • Hanging racks
  • Sanitary garbage disposal
  • Metal rack
  Sub total:  $5150
  -plus ~15% contingency funds         
  Total:  $6000


Language

We authorize the board to allocate space for the kitchen area as defined in Plan A. We authorize the board to spend up to $6000.00 for equipment, materials, and supplies to renovate the kitchen. The budgeted funds are valid for 8 months after the passing of this vote.