Line 32: Line 32:  
** Install work sink at the top of the stairs next to upstairs bathroom. $300
 
** Install work sink at the top of the stairs next to upstairs bathroom. $300
 
** Remove old sink in new lounge.
 
** Remove old sink in new lounge.
** Compressed air lines for the laser and hot metals. $250  Tom Judge recently told us that the current air lines are in bad shape and should be replaced. Fitter Dave had design ideas. There wasn't enough time to plan for this vote, so if a replacement is warranted, another vote may be necessary.   
+
** Compressed air lines for the laser and hot metals. $250. Tom Judge recently told us that the current air lines in the 3519 shop are in bad shape and should be replaced. Fitter Dave had design ideas. We aren't sure of the condition of 3515 lines (that side of the building is newer, so they may be OK). There wasn't enough time to plan for this vote, so if a replacement is warranted, another vote may be necessary.   
    
* Partition between hot metals and woodworking in 3515.
 
* Partition between hot metals and woodworking in 3515.
Line 50: Line 50:  
This vote assumes that these tasks will be performed  by the landlord before we move in:
 
This vote assumes that these tasks will be performed  by the landlord before we move in:
   −
*Paint the walls.
+
*Paint the walls in 3515.
 
*Fix roof leaks.
 
*Fix roof leaks.
 
*Upgrade the lighting.
 
*Upgrade the lighting.
   −
Sub total: $7750
+
Sub total: $8466
 
         plus 20% contingency funds
 
         plus 20% contingency funds
 
         minus $5000 already allocated in 2016 budget vote
 
         minus $5000 already allocated in 2016 budget vote
Total      $4300
+
Total      $5159.20
    
== Language ==
 
== Language ==
We authorize the board to spend up to $4300, in addition to the $5000 already voted on in the 2016 budget, for tools, materials, supplies and services to build-out plan 1 as described by the Space Planning Committee.
+
We authorize the board to spend up to $5159.20, in addition to the $5000 already voted on in the 2016 budget, for tools, materials, supplies and services to build-out plan 1 as described by the Space Planning Committee.
    
We also authorize the board to select a project manager who will create a plan, track expenses, organize volunteers and hire contractors.  The project manager will provide periodic reports to the board. The project manager will consult with the membership, area hosts, board and space planning committee when appropriate.
 
We also authorize the board to select a project manager who will create a plan, track expenses, organize volunteers and hire contractors.  The project manager will provide periodic reports to the board. The project manager will consult with the membership, area hosts, board and space planning committee when appropriate.
Line 69: Line 69:     
== Voting ==
 
== Voting ==
 +
Vote passes
   −
xx Yea, xx Nay, xx  Present
+
58 full members present
   −
Quorum was xx
+
56 Yea, 0 Nay, 2 abstained
 +
 
 +
Quorum was 41
    
[[Category:Votes]]
 
[[Category:Votes]]
 
[[Category:2016 Votes]]
 
[[Category:2016 Votes]]