Line 10: |
Line 10: |
| | | |
| == Background == | | == Background == |
− | We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link). This Build-Out vote describes how the initial build-out of the combined spaces will occur. We allocated $5000 for buildout expenses through the 2016 budget vote. | + | We signed the lease for the 3515 Elston and move in soon. The space planning committee created three floor plans for the combined space. Through a survey, the full members selected plan #1 (insert link). |
| | | |
− | This Build-out vote describes The 2016 budget vote allocated $5000 for build-out expenses. | + | This Build-Out vote describes the initial build-out of the combined space. The type of wall or partition required to separate woodworking and hot metals has not been determined, so an estimate for that is not included. A vote for additional money for the wall may be necessary. |
− | * HVAC | + | |
| + | The 2016 budget vote allocated $5000 for build-out. The expenses for the activities listed below should fall within that budget. If there are unforeseen expenses another vote may be necessary. |
| + | |
| + | * HVAC |
| ** Install AC in new lounge. $300 | | ** Install AC in new lounge. $300 |
| ** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser. The roof perforation will be done by a professional roofer. Interior ducting can be done by volunteers. Makeup air? Materials: ducting, elbows, hangers. $300 | | ** Install a 4" ventilation duct and fan in the clean CNC room to be used by the laser. The roof perforation will be done by a professional roofer. Interior ducting can be done by volunteers. Makeup air? Materials: ducting, elbows, hangers. $300 |
Line 29: |
Line 32: |
| ** Install work sink at the top of the stairs next to upstairs bathroom. $300 | | ** Install work sink at the top of the stairs next to upstairs bathroom. $300 |
| ** Remove old sink in new lounge. | | ** Remove old sink in new lounge. |
− | | + | ** Compressed air for the |
| *Obtain necessary permits if they are deemed appropriate. | | *Obtain necessary permits if they are deemed appropriate. |
− |
| |
| *Remove temporary partition in new lounge. Paint and repair drywall if necessary. Materials: paint. | | *Remove temporary partition in new lounge. Paint and repair drywall if necessary. Materials: paint. |
− |
| |
| *Move equipment to new locations. | | *Move equipment to new locations. |
− | | + | * Vacuum dust from trusses, walls, etc. in 3519 shop. |
− | * Clean dust from trusses, walls, etc. in 3519 shop. | |
| *Remove tool cage walls. | | *Remove tool cage walls. |
− | | + | *Purchase and install shelving for member storage. $500 |
− | *Purchase and install shelving for member storage. $1000 | |
− |
| |
| *Benches for general work area. | | *Benches for general work area. |
− | | + | * Run compressed air for the laser and hot metals. $300 |
− | * Compressed air for new shop. {Run tubing from old shop? Or get additional compressor? Also need air for laser/ CNC?} | + | * Rent or purchase a section of rolling scaffolding. This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. $300 |
− | | |
− | * Rent or purchase a section of rolling scaffolding. This will be used in the shop to help with the work near the roof such as electrical, ducting & cleaning. | |
| | | |
| This vote assumes that these tasks will be performed by the landlord before we move in: | | This vote assumes that these tasks will be performed by the landlord before we move in: |